Case Study: A Winter Roof Replacement at the Holiday Inn Express & Suites in American Fork

Job overview: King Roofing replaced the wind- and hail-damaged shingle roof (roof replacement in American Fork) on the Holiday Inn Express & Suites in American Fork, Utah, while the hotel stayed open. We replaced damaged decking where needed and installed GAF Timberline HDZ® shingles with GAF Cobra® SnowCountry® exhaust vents. Parking and foot traffic were directed to a safe area, and the install took two days, plus a half day for cleanup.

Drone view of the finished Pewter Gray roof on the Holiday Inn Express & Suites in American Fork, Utah, with snow-covered Mount Timpanogos behind
After: the finished roof, with Mount Timpanogos behind.

Project at a glance

PropertyHoliday Inn Express & Suites, American Fork, Utah
BuildingThree stories, L-shaped, beside I-15
Roof replacedAbout 19,500 sq ft of pitched shingle roof, mostly 5/12 (the flat roof section was not part of our scope)
CauseWind and hail
DeckingDamaged decking replaced where needed
New roofGAF Timberline HDZ® shingles in Pewter Gray
UnderlaymentGAF WeatherWatch® leak barrier at eaves and valleys; GAF FeltBuster® synthetic underlayment
VentilationGAF Cobra® SnowCountry® exhaust ridge vent
CityCommercial roof permit; final inspection passed
InstallEarly January 2025: two days, plus a half day for cleanup and equipment removal
Hotel statusOpen throughout
Owner's out-of-pocket cost$5,000 deductible

The challenge

The hotel sits beside I-15, and its parking lots and entrances are busy around the clock. The roof is an L-shaped shingle roof over three floors, with long valleys and many vents and pipes. Drone photos of the original roof showed worn, patched and mismatched shingle areas.

The work had to be done in an American Fork winter without closing the hotel.

Drone view of the hotel's courtyard side with its original gray roof
Before: the original roof from the courtyard side.
Straight-down drone view of the original L-shaped roof, with patched and mismatched shingle areas
Before: patched and mismatched areas on the original roof.

Planning a reroof around an open hotel

Guests and parking. The hotel stayed open the whole time. Parking and foot traffic were directed to a safe area away from the work zone, marked with cones and caution tape.

Equipment. We set roll-off dumpsters right beside the building and used a rented telehandler to lift materials to the roof.

Cleanup. Crews picked up debris and ran a magnet sweep all around the building before leaving for the day. At the manager's request, the crew also removed two old satellite dishes from the roof.

The install

In early January 2025, the install took two days, with a half day for cleanup and equipment removal. Crews tore the roof off to the deck and replaced damaged decking where needed. Then they installed WeatherWatch ice and water leak barrier at the eaves and valleys, FeltBuster synthetic underlayment, Pro-Start® starter, Timberline HDZ shingles, and Seal-A-Ridge® caps over Cobra SnowCountry exhaust vents.

What we installed

  • GAF Timberline HDZ® shingles, Pewter Gray
  • GAF Seal-A-Ridge® hip and ridge caps, Pewter Gray
  • GAF Pro-Start® starter strip
  • GAF WeatherWatch® ice and water leak barrier at the eaves and valleys
  • GAF FeltBuster® synthetic underlayment
  • GAF Cobra® SnowCountry® exhaust ridge vent
  • White drip edge, step and L-flashing, counter flashing and new pipe flashings
  • Replacement decking where damaged

Code items for an American Fork roof

The local code requirements for this roof included ice barrier at the eaves, drip edge, valley liner and underlayment. We installed all four, and the roof passed the city's final inspection.

Results

Drone view of the finished roof on the L-shaped hotel
After: the finished roof just after the install.

The hotel stayed open throughout, and the new roof passed the city's final inspection.

The project total was about $136,400. The owner's out-of-pocket cost was their $5,000 deductible; the remaining, about $131,400, was covered through the approved claim. Every claim is different. Coverage depends on your policy and the carrier's decision.

Frequently asked questions

Can a hotel stay open during a roof replacement?

This one did. Parking and foot traffic were directed to a safe area away from the work zone, marked with cones and caution tape. Every property is different, so we plan access with the manager before work starts.

Can you replace a roof in a Utah winter?

It depends on the weather. This roof was replaced in early January 2025. Crews tore off the old roof and got the leak barrier and synthetic underlayment down before the shingles went on.

What happens if the roof deck is damaged under the old shingles?

Once the old shingles are off, the deck is exposed and we can see its condition. On this job, damaged decking was replaced where needed before the leak barrier and underlayment went down.

How do you keep nails and debris out of a hotel parking lot?

On this job, crews picked up debris and ran a magnet sweep around the whole building before leaving for the day. Dumpsters sat right next to the building, so debris didn't have to cross the lot.

Why use exhaust vents along the ridge of a big roof?

Ridge exhaust vents let warm, moist air out of the attic at the highest point of the roof. On this hotel, we installed GAF Cobra® SnowCountry® exhaust ridge vents.